Ceiling Tile Removal, Scanning and Installation Program

Oki Siksika,

Siksika Nation Engineering Services (SNES) would like to inform all employees and building visitors of the upcoming ceiling tile removal, scanning and installation activities across several departmental areas. 

The SNES Maintenance Team will commence ceiling tile installation in the Membership and Post Office areas on Tuesday, November 24, 2026, in the morning.

Additional work is scheduled to take place in phases between November 2026 and March 2027, as outlined below.

Planned Work Schedule

AreaCeiling Tile RemovalScanningCeiling Tile Installation
Membership & Post OfficeStarting Nov 24, 2026
AdministrationNov 30 – Dec 8, 2026Dec 9 – 11, 2026Dec 14, 2026 – Jan 7, 2027
TreasuryDec 9 – 17, 2026Dec 18, 2026Jan 8 – 18, 2027
JusticeDec 18, 2026 – Jan 11, 2027Jan 12, 2027Jan 19 – 27, 2027
Land ManagementJan 12 – 15, 2027Jan 18, 2027Jan 28 – Feb 5, 2027
HousingJan 18 – 26, 2027Jan 27, 2027Feb 8 – 18, 2027
Disability Services/Consultation/CorridorJan 27 – Feb 1, 2027Feb 2 – 3, 2027Feb 19 – Mar 1, 2027
SFS Resource CentreFeb 2 – 10, 2027Feb 11 – 12, 2027Mar 2 – 12, 2027
Family ServicesFeb 11 – 19, 2027Feb 22, 2027Mar 15 – 25, 2027

Work Coordination and Safety

SNES will coordinate directly with the affected departments to minimize disruption to daily operations and arrange for work to be performed when employees are not present in the affected work areas.

Employees and visitors are requested to respect temporary access restrictions and follow safety instructions while work is in progress.

The above schedule is subject to change based on site conditions, operational requirements and work progress. Any significant changes will be communicated to the affected departments.

For questions or coordination requirements, please contact Leon Maguire at LeonM@siksikanation.com.

We appreciate your patience, understanding and cooperation throughout this program.