Oki Siksika,
Siksika Nation Engineering Services (SNES) would like to inform all employees and building visitors of the upcoming ceiling tile removal, scanning and installation activities across several departmental areas.
The SNES Maintenance Team will commence ceiling tile installation in the Membership and Post Office areas on Tuesday, November 24, 2026, in the morning.
Additional work is scheduled to take place in phases between November 2026 and March 2027, as outlined below.
Planned Work Schedule
| Area | Ceiling Tile Removal | Scanning | Ceiling Tile Installation |
| Membership & Post Office | Starting Nov 24, 2026 | ||
| Administration | Nov 30 – Dec 8, 2026 | Dec 9 – 11, 2026 | Dec 14, 2026 – Jan 7, 2027 |
| Treasury | Dec 9 – 17, 2026 | Dec 18, 2026 | Jan 8 – 18, 2027 |
| Justice | Dec 18, 2026 – Jan 11, 2027 | Jan 12, 2027 | Jan 19 – 27, 2027 |
| Land Management | Jan 12 – 15, 2027 | Jan 18, 2027 | Jan 28 – Feb 5, 2027 |
| Housing | Jan 18 – 26, 2027 | Jan 27, 2027 | Feb 8 – 18, 2027 |
| Disability Services/Consultation/Corridor | Jan 27 – Feb 1, 2027 | Feb 2 – 3, 2027 | Feb 19 – Mar 1, 2027 |
| SFS Resource Centre | Feb 2 – 10, 2027 | Feb 11 – 12, 2027 | Mar 2 – 12, 2027 |
| Family Services | Feb 11 – 19, 2027 | Feb 22, 2027 | Mar 15 – 25, 2027 |
Work Coordination and Safety
SNES will coordinate directly with the affected departments to minimize disruption to daily operations and arrange for work to be performed when employees are not present in the affected work areas.
Employees and visitors are requested to respect temporary access restrictions and follow safety instructions while work is in progress.
The above schedule is subject to change based on site conditions, operational requirements and work progress. Any significant changes will be communicated to the affected departments.
For questions or coordination requirements, please contact Leon Maguire at LeonM@siksikanation.com.
We appreciate your patience, understanding and cooperation throughout this program.